Bader, J.-M.
Case history: Sasol’s optimization of the catalyst regeneration process for C5 isomerization
Process Control
/ Process Optimization
/ Refining
/ Americas
/ Analyzers
/ Asia/Pacific
/ Economics
/ Engineering & Design
/ Equipment
/ Europe
/ Information Systems
/ Management
/ Middle East
Advanced process control (APC) offers solutions to use full catalyst regenerator capacity safely and to generate substantial benefits. Significant yield increases and operating cost reductions can be ..
Use a systematized approach of good practices in pygas hydrogenation via APC
APC with inferential modeling was successfully applied to pygas hydrogenation units. The lengthening of the catalyst run length limits downtime for both the pygas unit and upstream units such as the steam cracker.
Use real-time optimization for low-sulfur gasoline production
As the main sulfur source in the gasoline pool, fluid catalytic cracker (FCC) gasoline cuts must undergo severe hydrodesulfurization (HDS) processing to achieve ultra-low-sulfur gasoline (ULSG) pool s..
Increase MTBE plant productivity
Applying advanced process control solutions enabled raising unit output without a major retrofit of existing equipment
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- OXEA confirms final investment decision for major capacity expansion at plant 7/10
- TotalEnergies ships to Asia the first cargo produced by the ECA LNG plant 7/10
- ADNOC L&S expands LNG fleet with order for four new carriers 7/10
- India's ONGC plans to build 13-MMbbl national strategic oil reserve 7/10
- Russian refineries, oil terminal, tankers hit, Ukraine says 7/10
- Tajikistan says it has 60 days' fuel in reserve amid Russian supply crunch 7/10
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction